Joseph Bulynko · Candidate exercise · Fictional scenario
01 / 08
A clearer path for every applicant
Four Q1 commitments
Audit readiness. Resident confidence. A plan that shows what every change costs.
06
Audit export
11
Safe account recovery
01
Clearer existing status
07
Email + SMS updates
Neighborly Software
HOME​​BRIDGE / Q1
One decision, four different lenses
Necessity sets the lane. Urgency sets the order. Severity describes an observed issue.
Joseph Bulynko · Candidate exercise · Fictional scenario
02 / 08
Must
Vital to the outcome
06
Highest / 1
Should
High value; can move
01 11 07 04 05
High / 2 · Medium / 3
Could
Opportunistic value
02 09 12
Low / 4
Will Not
No Q1 production build
03 08 10
Lowest / 5
SEVERITY
Critical · Major · Moderate · Minor · Minimal
No documented defect: unassessed here.
SERVICE CLASS
Feature additions · 09 may be perfective · 03/08/10 need a scope decision
Neighborly Software
HOME​​BRIDGE / Q1
Every candidate has a place
Now + Next are Q1 commitments. Later is uncommitted. All 12 items stay visible.
Joseph Bulynko · Candidate exercise · Fictional scenario
03 / 08
Neighborly Software
HOME​​BRIDGE / Q1
Baseline capacity and sequencing
Planning assumptions: 13 weeks, 5 engineers, 40% UX allocation. No delivery date is guaranteed.
Joseph Bulynko · Candidate exercise · Fictional scenario
04 / 08
13
4
4
36
8
13 operations + 4 discovery + 4 release reserved
36 planned + 8 free = 44 feature weeks
W1
W3
W5
W7
W9
W11
W13
06 Audit export
8 eng. weeks
11 Account recovery
6 eng. weeks
01 Status tracker
12 eng. weeks
07 Email + SMS
10 eng. weeks
Design: 3.75 / 4 weeks
Build WIP ≤ 2 · Design leads each build
Neighborly Software
HOME​​BRIDGE / Q1
A change in priority changes the promise
The live presentation lets the panel move the work and see the exchange.
Joseph Bulynko · Candidate exercise · Fictional scenario
05 / 08
Neighborly Software
HOME​​BRIDGE / Q1
Outcomes, not a shipping checklist
Proposed targets to agree after a baseline. None of these values are current results.
Joseph Bulynko · Candidate exercise · Fictional scenario
06 / 08
25%
lower status-call rate
Calls per 100 active applications Compare similar agency cohorts.
Target: 75% of the baseline rate
Audit ready
Customer accepts a dry-run export
80% recovery
Completed / initiated recovery attempts
95% accepted
Provider acceptance ≠ resident reading
Guardrails: no wrong-recipient disclosure; no worse completion; older-phone / slow-network tests.
Neighborly Software
HOME​​BRIDGE / Q1
Dependencies make the sequence real
The tracker screen is not the dependency. Reliable, agreed status data is.
Joseph Bulynko · Candidate exercise · Fictional scenario
07 / 08
Source audit events
06
Validated audit export
Agreed status model
01
Clear status + next action
07
Email + SMS
11
Safe portal access
Customer-approved fields Historical coverage
Freshness + comprehension Pine County usability check
Consent + safe content Retries + deduplication
Access enables adoption
Neighborly Software
HOME​​BRIDGE / Q1
Evidence that changes the plan
Discovery earns its place when it can alter a commitment.
Joseph Bulynko · Candidate exercise · Fictional scenario
08 / 08
Audit history is missing
Expand 06
Reduce 07 first
Calls reflect stalled work
Bring in 04 dashboard
Replace 07; review 01
Spanish is an essential barrier
Bring in 05 Spanish
Replace 11; recheck UX
Effort rises to 54 weeks
Keep 06 + 11 + 01
Defer 07; demand falls to 38
Protect the audit. Make status understandable. Name every tradeoff.